Opening or changing an X-ray facility in Nevada can feel confusing. This guide puts the state-level steps, forms, filing links, fees, and contacts in one place.
Get shielding help in Nevada
Planning an X-ray project in Nevada? Most rooms need a shielding design before registration. Send the floor plan — quotes come back within one business day.
Request a Shielding DesignHeartland Physics can review the project scope and confirm whether its current qualifications and authorization cover any shielding work required for this project. Use the current government sources linked below for registration, plan review, fees, inspections, and filing requirements.
Quick answer
Nevada registers facility X-ray machines through the CLICS online system. The facility is responsible for the registration and fees, and the certificate must be posted before use. The state says processing may take about 30 days.
Start here: official forms and filing links
Each blue button opens the exact official form, portal, or state instruction page in a new tab.
What to gather before you start
• Nevada facility legal name, address, owner, and contact
• Radiation-safety contact
• Machine manufacturer, model, serial number, type, room, and installation date
• Shielding design and room records
• Installer and acceptance-test records
• Online payment method
Step-by-step instructions
Step 1: Plan the room and shielding
Address room shielding before construction or installation and retain the final design and supporting records. Heartland Physics can review the Nevada project and confirm whether its current qualifications and authorization cover the shielding work.
Step 2: Create a CLICS account
Open the Nevada CLICS link. Register the facility user and confirm the email address.
Step 3: Apply for machine registration
Choose the radiation-producing machine registration. Enter the Nevada facility, responsible person, room, and machine information. Upload requested documents.
Step 4: Pay and wait for the certificate
Pay the online charges and save the confirmation. Allow about 30 days for processing. Nevada does not normally require a state inspection before initial use, but the registration certificate must be posted before operation.
Step 5: Use CLICS for later changes
Update the registration when a unit is added, moved, replaced, transferred, stored, or removed. Renew and pay fees when the system sends the notice.
Cost
Nevada calculates registration fees from the facility and machine information entered in CLICS.
State contact
Nevada Radiation Control Program: radiationcontrolprogram@health.nv.gov.
Keep these records together
• Submitted application and payment receipt
• Current registration certificate or license
• Shielding design, calculations, and state review letter when applicable
• Installer paperwork, FDA Form 2579 when applicable, acceptance tests, and equipment-performance reports
• Operating procedures, staff training, dosimetry, maintenance, and inspection records that apply to the facility
Important reminder
This guide covers the usual state-level radiation-machine process. Mammography, radiation therapy, mobile use, healing-arts screening, and some industrial systems can have extra approvals. Complete those extra steps when they apply to your equipment.
Official sources
Use the current government sources linked on this page. Requirements, forms, fees, contacts, and procedures can change.
Get shielding help in Nevada
Planning an X-ray project in Nevada? Most rooms need a shielding design before registration. Send the floor plan — quotes come back within one business day.
Request a Shielding DesignLast updated Aug 21
Next step
Need a shielding design for your project?
Send the basics through the structured request form — we respond within one business day.